Big River Trenchless & GeoServices has embarked on numerous projects ranging in scopes and sizes. Our experience working through various project environments and complexities allows us to provide innovative solutions to meet the needs of any project.

Manhattan West- North Tower

Manhattan West- North Tower

  • Drilled and installed 82 – 16” diameter rock anchors with design load of 922.5 tons.
  • Anchors consisted of 3 thread bars in one drilled hole with lengths of 63’ and 83’.
  • Utilized the largest solid bar capacity anchors in the world.

NYCDEP 26th Ward Wastewater Treatment Plant

NYCDEP 26th Ward Wastewater Treatment Plant

• Stelcor piles
• Drilled Displacement Piles
• (2) new clarifier tanks
• Pump and piping upgrades
• No spoils, no vibration

King’s Highway

King’s Highway

  • Installation of (36) 10 ¾ pressure mounted micro piles
  • New signal building for MTA
  • Surroundings included school, retail, and grocery stores with heavy pedestrian traffic
  • Vehicular traffic

Canarsie Tunnel Rehabilitation

Canarsie Tunnel Rehabilitation

• Support of excavation
• Soldier piles
• Residential, high traffic area

PS 254 – Drilled Displacement Piles

PS 254 – Drilled Displacement Piles

• Foundation support for new school in Brooklyn
• Installation of drilled displacement piles
• Installation of helical piles
• No spoil, low vibration application

Belmont Park Arena

Belmont Park Arena

• Installation of steel sheet piles
• Support of Excavation
• Stadium development construction site

Oltorf Water Main 60” MTBM

Oltorf Water Main 60” MTBM

• Excavate and install Liner Plate Shafts (Launch – 30’ Diameter, Reception – 22’ Diameter)
• Install 60” Tri-loc Casing using Micro Tunneling methodology (478 LF)
• Contact Grout annulus of 60” Tri-loc casing
• Install 36” Water Line through 60” casing
• Cellular Grout the annular space between product pipe and casing
• Install vertical stand pipe of 36” water line – including installation of 36” welded Tee
• Flowable backfill in shafts up to installed

Zacate Creek WWTP to Chacon Creek Interceptor

Zacate Creek WWTP to Chacon Creek Interceptor

• Install liner plate shafts (launch-22”, reception-22”)
• Install 235 LF of 60” Tri-loc casing using Micro Tunneling
• Contact grout annulus of 60” casing
• Install 6200 LF of 42” Hobas FRP casing inside 60” casing
• Apply cellular group annular space between product pipe and casing
• Construct 500 LF of aerial crossing
• Install manholes using open cut methodology
• Install sanitary bypass systems

Park Ten Wastewater Treatment Plant Tunneling

Park Ten Wastewater Treatment Plant Tunneling

• Install 42” Tri-loc casing using Micro Tunneling methodology (1734)
• Contact Grout annulus of 42” casing
• Install 28” FRP Sanitary Sewer using Micro Tunneling methodology (3191 LF)
• Contact Grout annulus of 28” casing

FWSD #23 Tunneling

FWSD #23 Tunneling

• 811 Mark-out
• Install 72” Steel Casing using Micro Tunneling
• Contact Grout annulus of 72” casing